  151:当项目接近完工时:

  As a project approaches completion:

  A:就不再需要风险管理

  Risk management is no longer needed

   B:变更成本一般会增加

  The cost of changes typically increase

   C:高风险项的有能性会增加

  The probability of high-risk items increases

   D:不再需要应急储备

  Contingency reserves are no longer needed

  152:客户要求新产品必须尽快推向市场,客户要求项目经理进一步压缩项目进度,项目经理接下来应该怎么做?

  The customer requests the new product to be on the market as soon as possible,the customer asks the project manager to further compress the project progress,what should the project manager do next?

  A:告知客户进度无法更改

  Informing the customer that the progress cannot be changed

   B:要求客户提交变更请求

  Request a customer to submit a change request

   C:修订关键路径并将新进度通知团队

  Revise critical paths and notify the team of new progress

   D:协商变更范围,并压缩进度

  Negotiate the scope of changes and compress progress

  153:项目经理被要求为两个潜在项目执行成本效益分析。项目A成本为$12亿美元,潜在效益为$60亿美元,未来运营成本为$15亿美元;项目B成本为$14亿美元,潜在效益为$70亿美元,未来运营成本为$1亿美元。项目经理应该推荐哪一个项目?

  A project manager is asked to perform a cost-benefit analysis for two potential Project A costs US$1.2billion.With potential benefits of US$6 billion and future US$1.5 billion.Project B costs US$1.4 billion,with potential benefits of US$7 billion and future US$1 billion.Which

  project should the project manager recommend?

  A:项目B;因为潜在效益减去执行成本所得的值大于项目A所得值。

  Project B;the potential benefits minus the costs to implement are greater calculation for project

   B:项目A;因为执行成本低于项目B。

  Project A;the cost to implement is less than project

   C:项目B;因为潜在效益减去执行成本和未来运营成本所得的值大于项目A。

  Project B;the potential benefits minus the implementation and future greater than the same calculation for project A.

   D:项目A;因为潜在效益加上未来运营成本所得的值小于项目B所得值。

  Project A;the potential benefits plus the future operating costs are less than calculation for project B.

  154:项目经理与项目相关方开会,收集需求并制作项目需求文档。项目经理下一步该怎么做?

  The project manager meets with the stakeholders,gathers requirements,and develop the project requirement documentation.What should the project manager do next?

  A:制定需求基准,并获得关键关系人的批准

  Baseline the requirement and obtain key stakeholders approve

   B:与团队一起创建工作分解结构

  Create the work breakdown structure with team

   C:准备一份详细的项目范围说明书

  Prepare a detailed project scope statement

   D:制定项目管理计划

  Develop a project management plan

  155:风险评估师在哪一个项目风险管理过程中执行的?

  During which project risk management process is risk assessment performed?

  A:制定风险管理计划

  Plan Risk Management

   B:识别风险

  Identify Risks

   C:开展定性风险分析

  Perform Qualitative Risk Analysis

   D:规划风险应对

  Plan Risk Responses

  156:在项目评审会上,从事活动AD的项目团队成员通知项目经理,完成该活动还需要三天,组织的高级经理要求项目经理,即使需要额外的预算,也必须找到方法,按原定基准计划支付项目。项目应该使用什么方法来满足高级经理的需求?(图)

PMP试题

  During a project review meeting,the project team member working on activity AD advises the project manager that it will take three more days to complete the activity.The organization's senior manager asks the project manager to find ways to deliver the project according to the original baseline plan,even though it may need additional budget.What should the project manager use to meet the senior manager's needs?

  A:使用快速跟进

  Use fast tracking

   B:使用赶工

  Use fast crashing

   C:应用关键链法

  Apply critical chain method

   D:应用时间提前量和时间滞后量

  Apply leads and lags

  157:你决定要在公司中组建一个PMP考试的学习小组,邀请公司内部其他的项目经理一起参加,以此帮助大家更好地准备这次考试。由于公司总经理已经决定要奖励每个通过考试的人5000美元,所以每个人都有了很强的动力要通过考试。那么,在组织这个学习小组的过程中你要采用什么类型的沟通方式呢?

  You have decided to organize a study group of other project managers in your organization to help prepare for the PMP exam.Everyone is highly motivated to earn the credential because the CEO has decided to pay a¥5,000 bonus to each person who becomes certified.What type of communication are you employing in your efforts to organize this group?

  A:横向沟通

  Horizontal

   B:向下沟通

  Vertical

   C:正式沟通

  Formal

   D:外部沟通

  External

  158:这个图中的关键路径是什么?

PMP试题

  In this diagram,what is the critical path?

  A:B-F-J

  B-F-J

   B:B-E-H-J

  B-E-H-J

   C:B-D-H-J

  B-D-H-J

   D:C-G-I-J

  C-G-I-J

  159:项目经理完成了项目章程。项目经理需要做的下一个活动是什么?

  The project manager completes the project charter.What is the next activity the project manager needs to do?

  A:创建详细的相关方登记册

  Create Detailed stakeholder register

   B:创建需求文件

  Create requirements documentation

   C:创建相关方管理策略

  Create stakeholder management strategy

   D:创建质量管理计划

  Create quality management plan

  160:项目经理完成了一个需要从当地供应商采购设备的大型项目。下

  列哪一项活动能发生在结束采购过程中?

  A project manager completes a large project that requires equipment purchases from a local vendor.Which of the following activities would occur in the close Procurement’s process?

  A:更新采购管理计划

  Updating the procurement management plan

   B:更新合同条款和调节

  Updating the terms and conditions of contract

   C:合同文档存档

  Archiving the contract documentation

   D:项目管理计划存档

  Archiving the project management plan

  本期答案:
 
  151、正确答案:B
 
  解析:参见2.4.1项目生命周期的特征,变更和纠正错误的代价在项目接近完成时通常会显著提高,所以选B。考点:项目生命周期特征。
 
  152、正确答案:B
 
  解析:压缩关键路径上的活动才能够对项目进度压缩,影响关键路径上的活动,应提交变更请求。
 
  153、正确答案:C
 
  解析:商业论证从商业视角描述必要的信息,并且据此决定项目的期望结果是否值得所需投资。高于项目级别的经理和高管们通常使用该文件作为决策的依据。一般情况下,商业论证会包含商业需求和成本效益分析。收益=潜在效益-投资成本-运营成本
 
  154、正确答案:C
 
  解析:见PMBOK5/5.3/定义范围。从需求文件中选取最终的项目需求,然后制定出关于项目及其产品、服务或成果的详细描述。
 
  155、正确答案:C
 
  解析:出处:11.3.2.3。实施定性风险分析工具与技术包含数据分析;数据分析包含风险的质量评估、概率和影响评估,及参数评估。
 
  156、正确答案:B
 
  解析:指南-6.5.2.6进度压缩,赶工。题中提到了“额外的预算”,即多花钱是可以的,一般表现为加班,加人,达到赶工的目的。
 
  157、正确答案:A
 
  解析:横向沟通:针对项目经理或团队的同级人员
 
  158、正确答案:B
 
  解析:见PMBOK5/6.6.2.2/关键路径。由图可以得出:BEHJ持续时间=2+6+3+3=14。这条路径最长。无图
 
  159、正确答案:A
 
  解析:考点:识别相关方。4个选项活动顺序依次为A-C-B-D,相关方登记册是制定质量管理计划的依据。
 
  160、正确答案:C
 
  解析:见PMBOK5/12.4.2.3/记录管理系统-存档。项目经理采用记录管理系统来管理合同、采购文档和相关记录。通过记录管理系统把合同文件和往来函件存档,这是结束采购过程的一项工作




 
关于我们PMP动态PMP报考信息PMP认证PMP培训服务PMP备考专区 PMP考试费用
友情链接: PMI  重庆成人高考  猎聘网   中国考研网   IT世界网  中国IT 人才网  
PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc.
慧翔天地管理咨询集团 版权所有 京ICP备13007601号-1